Aluminium Profile Finishes: GB/T 5237 Series & RFQ Checklist

铝型材表面处理怎么选:GB/T 5237 六个分部与询价验收清单
2026-11-07
Aluminium profilesSurface finishesGB/T 5237
Aluminium Profile Finishes: GB/T 5237 Series & RFQ Checklist

Writing '6063-T5 aluminium profile, coated finish' on an RFQ sounds complete and says almost nothing. Anodised, electrodeposition-coated, powder-coated, paint-coated and thermal-barrier profiles each carry a different set of acceptance criteria, test items and warranty terms. Worse, the film-thickness comparison tables circulating online contradict one another, so copying a number into a contract is a reliable way to create a dispute at incoming inspection. This guide follows the order a buyer actually works in: which documents make up GB/T 5237, what each finish family is for, which numbers must not be copied, and a checklist that can be pasted straight into an enquiry and an inspection form.

1. GB/T 5237 is a six-part series, not one standard

On the national standards information platform, the current edition of GB/T 5237 is the 2017 series. Each of the six parts has its own number and title, and all six were published on 14 October 2017. Parts 1, 2, 3, 5 and 6 took effect on 1 July 2018; Part 4 took effect on 1 May 2018. Referring to 'GB/T 5237-2017 Architectural Aluminium Profiles' as a single document is a common and costly error in purchasing paperwork, and one that reviewers routinely send back.

PartOfficial titleWhat it governs
GB/T 5237.1-2017Part 1: Base profilesAlloy designation, temper, chemistry, dimensional tolerance, mechanical properties
GB/T 5237.2-2017Part 2: Anodized profilesAnodic film thickness grades, sealing quality, appearance, corrosion resistance
GB/T 5237.3-2017Part 3: Electrodeposition coating profilesComposite film of anodic oxide plus electrophoretic lacquer
GB/T 5237.4-2017Part 4: Powder coating profilesThermoset powder coating
GB/T 5237.5-2017Part 5: Paint coating profilesLiquid paint systems, including fluorocarbon coatings
GB/T 5237.6-2017Part 6: Thermal barrier profilesInserted-strip and poured-and-debridged construction

Two titles are misquoted constantly. Part 4 is officially 'Powder coating profiles' and Part 5 is 'Paint coating profiles'; the 2008 edition of Part 5 was indeed titled fluorocarbon-paint sprayed profiles, but the 2017 edition fully replaced it and broadened the scope. A contract that still cites GB/T 5237.5-2008 points at a withdrawn standard. One more correction: some online buying guides tell you to check a '3C certificate' for aluminium profiles. Architectural extrusions are not in the mandatory product certification catalogue. At goods receipt the documents that matter are the certificate of conformity, the quality certificate and the test report.

2. What each finish family actually solves

Anodizing (Part 2)

An oxide layer is grown from the aluminium itself, so the metallic character is preserved and the dimensional impact is minimal. Colours are limited to silver, bronze, black and similar tones, and the surface resists wiping and abrasion well. It suits visible interior elements and projects where a genuine metal appearance is required. Because batch-to-batch tone can drift, agree a sealed sample and a batch consistency clause before production.

Electrodeposition coating (Part 3)

A lacquer layer is deposited over the anodic film, forming a composite coating. The result is more uniform than plain anodizing, more resistant to fingerprints and staining, and available in a wider gloss range. It fits windows and decorative profiles where appearance consistency matters more than a thick coating.

Powder coating (Part 4)

Electrostatic powder coating offers the widest colour and texture choice, including wood-grain transfer, at manageable cost. It is the default for exposed window, door and railing profiles. Specify the powder chemistry, colour code, gloss level, adhesion and weathering test items, and define explicitly which faces count as decorative.

Paint coating (Part 5, including fluorocarbon systems)

Liquid coating systems with two, three or more coats are selected against the standard and the project documents. Fluorocarbon systems are typically chosen for high-durability facades and curtain walls. The decision should rest on exposure category, design service life and an approved sample, not on the assumption that more coats are always better.

Thermal barrier (Part 6)

Strictly speaking this is not a finish but a structural composite, either a polyamide strip inserted between two extrusions or a poured polymer channel. It determines the thermal path of the whole window, so the strip material and geometry need separate verification; polyamide strips, for example, are covered by GB/T 23615.1-2017. Treating the thermal break as a 'finish option' on the enquiry is one of the most frequent omissions.

3. Why film-thickness numbers from search results do not belong in a contract

Open two industry articles at random and the numbers collide. Anodized exterior profiles are quoted as 'Class A, at least 12 micrometres' in one and 'AA15, average at least 15 micrometres' in another. Powder coating appears as 'decorative face at least 50 micrometres', 'local minimum 40 micrometres' and 'average 60 micrometres'. Three-coat paint systems appear as 30, 34 and 40 micrometres. Most of these figures never say whether they come from the standard text, a specific test condition or a factory's internal target. They also tend to treat 'exterior versus interior' as a universal grading rule, ignoring the exposure category and the project specification. Marketing phrases such as '15 to 20 years of weatherability' are worse: they cannot be tested and cannot be enforced.

There is a defensible three-step alternative. First, put the grade designation in the contract, chosen from the relevant part of the standard and the purchaser's requirements rather than as a bare thickness figure. Second, put measured values in the test report: film or coating thickness, adhesion, sealing quality and weathering results issued under the test methods specified in the standard, with CMA or CNAS accreditation and full specimen details. Third, put the decision rule in the acceptance clause: sampling lot, judgement group, retest procedure and nonconformance handling. The numbers themselves come from the standard text and the project technical documents, never from a search snippet.

4. Eight items every RFQ must state

  1. Application and exposure: window, curtain wall or interior trim; coastal, industrial-atmosphere or general urban setting. Describe the environment; do not invent thresholds.
  2. Base metal: alloy designation and temper, for example 6063-T5, to GB/T 5237.1-2017.
  3. Section and tolerance: attach the section drawing, state the dimensional tolerance grade and critical mating dimensions. The drawing wins over prose.
  4. Finish: part number of GB/T 5237, grade designation, colour and gloss sample reference, and the defined decorative faces.
  5. Thermal break: inserted strip or poured, strip material designation, width and batch consistency.
  6. Cut length and packing: delivery length, cutting tolerance, end protection, protective film and packing method.
  7. Accompanying documents: certificate of conformity, quality certificate, type-test report, laboratory accreditation and the link between report and batch.
  8. Acceptance terms: sampling plan, measured items, judgement basis, retest and return or replacement procedure.

For window and facade work, start with our window and door profiles and thermal-break casement profiles. Inserted-strip systems need a separate check of the polyamide thermal break strips, and where a fluorocarbon-painted facade is involved, align the colour and weathering requirements of the PVDF-coated aluminium veneer at the same time. If the section is not fixed or is non-standard, use the contact page to send drawings with the enquiry; that produces a far more useful answer than comparing a price per metre.

5. Structuring an incoming inspection form

CheckWhat to look atAction on failure
DocumentsModel, lot, part number and grade designation against the contractHold unloading; obtain documents or replace
AppearanceColour drift, scratches, runs, orange peel, end burrs, compared with the sealed sampleQuarantine the lot and judge by batch
DimensionsCritical section dimensions, wall thickness, bow and twist, measured to drawing and tolerance gradeSegregate out-of-tolerance pieces, then retest
Film and coatingThickness records, adhesion, sealing quality, third-party report cross-checkWitnessed sampling and laboratory judgement
Marking and traceabilityCertificate, lot number, package label and packing list all matchingReject any lot that cannot be traced

Record measured values and the pass or fail decision, never 'visually acceptable'. Log the gauge model, measuring positions, sample size and judgement basis. If colour drift or coating failure appears six months later, that record lets you go back to a specific lot rather than to a verbal assurance nobody can reconstruct.

6. Frequently asked questions

Q: Is 'complies with GB/T 5237' enough in a contract?

No. The series has six parts. State the part, the grade designation and the edition. Naming only the series lets a supplier deliver to the loosest plausible reading.

Q: Can anodizing and powder coating be swapped?

Not automatically. Appearance, corrosion mechanism, test items and repair methods all differ. A substitution is a design change and needs a new sample, a new report and a revised contract annex.

Q: Are more fluorocarbon coats always better?

No. The coating system must match exposure category, design service life and budget, and must be fixed under Part 5 and the project documents. Adding coats raises cost and can introduce adhesion or flexibility risks.

Q: Why insist on a sealed sample?

Colour, gloss and texture cannot be defined precisely in words. A sealed sample is the only object that can be compared again at delivery, at retest and on a later top-up order. Without it, a colour dispute is effectively undecidable.

Q: Does the thermal break strip need its own acceptance check?

Yes. Part 6 governs the composite profile's construction and performance, while the strip material has its own standard. Request both sets of documents and match them to the same lot.

Insights

Insights

View all insights

Send us your list

Send us the categories, models or opening sizes you need. We will organise the configuration and quotation, in Chinese or English.