A compliant whole-window test report proves what a product can do in a laboratory. Installation acceptance answers a different question: what this particular window still does once it has been fixed into this particular wall. The same model, from the same batch of extrusions, can produce very different air and water tightness results depending on the installation crew, and the cause is rarely the aluminium itself. It is the ring of interface between frame and wall. This guide does not repeat how to read a test report; it covers what to check at handover, which numbers circulating online must not become acceptance criteria, and a checklist that belongs in a contract annex.
| Document | Scope | Effective date |
|---|---|---|
| GB/T 8478-2020, Aluminium windows and doors | Product classification, requirements, test methods and accompanying documents | 1 February 2021 |
| GB/T 39529-2020, General technical requirements for system windows and doors | System rules, material substitution and process requirements fixed in documented form | 1 November 2021 |
| JGJ 214-2010, Technical code for aluminium window and door engineering | Design, fabrication, installation, engineering acceptance and maintenance | 1 March 2011 |
| GB 50210-2018, Standard for construction quality acceptance of building decoration | Acceptance of the window and door subdivision, including external wall waterproofing | 1 September 2018 |
| GB 55030-2022, General code for waterproofing of buildings and municipal engineering | Mandatory engineering code; all clauses must be applied | 1 April 2023 |
Pay particular attention to the last row. GB 55030-2022 is a mandatory engineering code, and where existing engineering standards conflict with it, the code prevails. Many installation articles still describe a single bead of sealant as sufficient, an approach inherited from older clauses that neither reflects multiple lines of defence and design working life nor necessarily satisfies current mandatory requirements. A contract annex should say 'comply with the current mandatory engineering codes and the approved shop drawings', not reproduce a list of practices copied from a blog.
This is the number one source of leakage. The gap fill must be dense and void-free, and the exterior weatherproof sealant continuous, unbroken and bonded to both frame and substrate. Typical mistakes include trimming foam flush and then applying only a thin skim of sealant, leaving holes from temporary wedges unfilled, and missing the joints between mullion extensions. Timing matters as much as the result: gap filling and sealant application are concealed or interim operations and should be photographed before finishes cover them.
A system window drains and directs water rather than merely blocking it. Check that weep holes are clear, that drainage channels connect to them, that external discharge is unobstructed, and that sill slopes and drip edges follow GB 55030-2022 and the shop drawings. A weep hole blocked by foam or mortar after installation is more dangerous than a missing bead of sealant, because water then accumulates inside the chamber and finds its own way out.
Corner jointing, corner sealing and the connections between coupled frames largely determine whole-window watertightness. These sit at the boundary between factory fabrication and site assembly, so at handover they should be traceable to the process requirements in the system documentation, not repaired on the spot with an extra bead of sealant.
Verify glazing block positions, that glass does not bear directly on aluminium, that gaskets run continuously without gaps or pulled corners, and that locking points compress the gasket evenly when closed. Gasket material and the number of seal lines must match the system documentation; substituting a cheaper gasket is a change to the system itself.
Installation articles quote wildly different spray durations: 10 to 15 minutes, 15 to 20 minutes, or 'at least one hour'. The figures contradict each other and almost never state spray pressure, flow rate, coverage, observation period or pass criteria. Write any one of them into a contract and the site team either cannot reproduce the test or the two parties end up arguing about what counts as a pass.
The workable formulation is to fix five things in the contract and in an approved acceptance plan: spray coverage (whole window, opening sash, frame-to-wall joint, mullion joints and sill), spray conditions (pressure, flow rate and nozzle distance per the plan or a referenced test method), duration and observation period, pass criteria (no leakage, no damp staining and no standing water on the interior), and door-by-door records with rectification and retesting. Where required, carry out sample on-site air and water tightness testing of external windows under GB 50210-2018 and the corresponding test method standards. Re-inspecting after heavy rain or a typhoon season says more about real behaviour than a single spray on handover day.
The configuration cross-check is equally direct: the ES92MD integrated-screen system window fixes the whole-window system and opening mode, EPDM gaskets and weatherproof silicone sealant govern the gasket lines and exterior joint, and polyamide thermal break strips are what site fixings must not damage. When a project needs an installation plan by window type, opening and climate, send drawings through the contact page; that gets you much closer to a result that survives acceptance than asking only for a price per square metre.
Product protection must continue until internal and external finishes are closed up; removing protective film too early exposes profiles and gaskets to contamination and scratches from following trades. Sealants need the curing time stated in the product documentation, and washing or covering before cure wastes the work. At handover, file the water-test records, concealed-work images, material batch numbers and maintenance instructions together, and agree a periodic reinspection schedule. Waterproofing is a design-working-life obligation, not a one-off event on completion day.
Yes. The report proves the product and process combination in a laboratory; the on-site test verifies this wall, this opening and this installation. Neither substitutes for the other.
There is no universal number to copy. The contract and approved acceptance plan should fix spray conditions, duration, observation period and pass criteria, with a record for each window. Do not write contradictory blog figures into a contract.
No. Bead width and depth, substrate preparation, compatibility and continuity are set by the design and product documentation. Piling sealant over a void in the gap fill tends to crack once thermal movement starts.
Because even good seals age or fail locally. Giving water that enters the chamber an orderly path back outside, then adding redundant seal lines, is what the multiple-lines-of-defence approach in GB 55030-2022 requires.
No. Those figures are usually unsourced and contradictory. Check wall thickness against GB/T 8478-2020 and the project documents, and fixing positions, gaps and slopes against the shop drawings and current codes. The acceptance record should contain measured values and a pass or fail decision.

GB/T 5237.6-2017 and GB/T 23615.1-2017 govern two different goods. Read both markings before you sign the packing list.
Read more
QB/T 2698-2024 covers overhead closers and excludes fire door closers. QB/T 2697-2024 covers floor springs. Fix the scope first.